Quantcast
Channel: SCN: Message List
Viewing all articles
Browse latest Browse all 9564

Viewing requirements generated after running MRP (MD50)

$
0
0

Hi All,

 

I would like to know if there is any way to check for all the requirements that have been raised subsequent to running MRP using MD50. We have an MTO scenario and want to cross-check if the requirements for raw materials are being accurately generated.

 

This cross-checking requirement has risen due to the fact that there are many alternative BOMs for each material and there have been instances where due to errors in the material master, some raw materials are suspected to be missing out from the list of requirements generated.

 

 

Thanks!

 

Praveer


Viewing all articles
Browse latest Browse all 9564

Trending Articles



<script src="https://jsc.adskeeper.com/r/s/rssing.com.1596347.js" async> </script>