Hello,
I have a question with regards to the line appeared in the ME2O corresponds to my delivery schedule lines in my Schedule Agreement (SA).
The following is my delivery schedule in my SA.
The relationship between the parent (#0001062) and child (#02210349) in the BOM is 1 to 1.
The following are the ME2O display when I run it for the subcontract vendor and the parent material.
In order for better view, I combined the two above screen into one following, and you will notice that ME20 only proposes those Delivery Schedule Lines indicated in yellow.
Question:
I look through the delivery date between two screens and seem it doesn’t make any why those white color line not propose in the ME2O screen, does it means those components in white row does not need to replenish to the subcontractor, if yes, it doesn’t make sense to me, and am sure I am missing out something. Do you know?
The following is the MD04 for the parent material, and highlights below are proposed in MD04 screen of child component, which also shown in ME2O screen for the child component:
And the following MD04 is the child:
Regards,
Daniel